The latest official figures for July, 2012, shows that ADPC’s flagship Khalifa Port is less than 2% from completion.
The Port, whose new semi-automated container terminal opens on September 1st, is 98.48% complete.
Khalifa Industrial Zone Abu Dhabi (Kizad), adjacent to the Port, is 90.87% complete. The industrial zone will grow into one of the largest ones in the world.
Overall, the adjusted completion figure for the Taweelah megaproject (both Khalifa Port and Kizad combined) is 96.63% complete.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.